CITY LOFTS

PROJECT: In Progress

>> The Quays Salford

CLIENT
Zenith Management Limited / Thomasons
MAIN CONTRACTOR
Envirosips Ltd

Envirosips  were awarded phase one of the remediation of City Lofts on Salford Quays. This involves the removal of combustible ACM cladding and PIR insulation which forms the roof top perimeter detail. Timber framework that forms terrace sun-screening is also being replaced.

All replacement materials are A1/A2 compliant including mineral wool insulation, cavity fire barriers and fire stops,  a 3mm aluminium hook on cassette system and CS airfoil Breise Solail.

Works are due for completion in early August 2021.